Skip to main content

Chapter 10 Homework Assignment




Chapter 10

Questions

1.      Determine the schedule and cost variance for a project that has an actual cost at month 20 of $750,000, a scheduled cost of $600,000 and an earned value of $700,000.

2.      Determine the schedule variance, cost variance, SPI, CPI, and CSI for a project that has an actual cost at month 12 of $90,000, a scheduled cost of $100,000 and an earned value of $120,000.

3.      A software development project at day 60 exhibits an actual cost of $300,000 and a scheduled cost of $375,000.  The software manager estimates a value completed of $300,000.  Determine the schedule variance, cost variance, SPI, CPI, and time variance for the project.

4.      A project to develop a county park has an actual cost in month 24of $240,000, a planned cost of $290,000, and a value completed of $80,000. Determine the schedule variance, cost variance, SPI, CPI, and CSI for the project.


Comments

  1. https://www.chegg.com/homework-help/questions-and-answers/parachutist-mass-70-kg-jumps-plane-altitude-32-km-surface-earth-unfortunately-parachute-fa-q5850901

    ReplyDelete

Post a Comment

Popular posts from this blog

Osmosis Data Sheet

Data Sheet: Activity - Osmosis Name Course Date Activity Data Code       Procedure I -Test Solution 1: Water Complete the tablesand questions below using your data and information found under the Background tab Data Table I Note: Difference in Final Volumes = Final Volume of Test Sol - Final Volume of Water Trial Starting Volume of Test Solution (L) Starting Volume of Water (L) Final Volume of Test Solution (L) Final Volume of Water (L) Difference in Final Volumes (L) 1 1.28 1.75 1.51 1.52 -0.01 2 1.28 2.00 1.64 1.64 0 Observations and Questions [1] Given that the final heights (and volumes) are the same for the water and test solution, what can you...
Simple Computer Science Questions Question 2 ANSWER Match the following a - 4 b - 10 c - 8 d - 6 e - 9 f - 1 g - 2 h - 7 i - 3 j - 5
Question: 7. A circular cam 200 mm in diameter rotates off centre with an eccentricity of 25 mm and operates the roller follower that is carried by the arm as shown in Fig. 23.35. ???200 mm +100mm- Spring 25 mm Fig. 23.35 The roller follower is held against the cam by means of an extension spring. Assuming that the force between the follower and the cam is approximately 250 N at the low position and 400 N at the high position. If the spring index is 7, find the diameter of wire, outside diameter of spring and the number of active coils. The maximum shear stress may be taken as 280 MPa. Use G 80 kN/mm2 ANSWER